PROJECT SPOTLIGHT | Hollywood Wastewater Treatment Plant

As the general contractor, our Wharton-Smith team constructed the Hollywood Wastewater Treatment Plant (WTP) on behalf of the Seminole Tribe of Florida (STOF).

The project consisted of a new three MGD WTP and now supports residential and business growth on the STOF’s Hollywood Reservation. The scope of work on this three-phase project included, but was not limited to:

▪ Phase 1: Installed 4,000 linear feet of 24” force main
▪ Phase 2: Produced injection well pump station
▪ Phase 3: Established new plant

We had the pleasure of completing this project in April 2020 with our partners, Hazen and Sawyer.

To learn more about this reclamation facility, check out our project page!